option2The Brownwood Independent School District school board approved three possible schematic designs for classroom additions to East Elementary Monday night.  Due to increased enrollment this year, the district has seen a need for the new expansion.

Daren Kirbo of Huckabee Architecture provided the board with three different schematic designs for the proposed expansion.  The first design was for an additional four classrooms to be constructed and the second and third designs were for six new classrooms, but with different configurations.

The district looks to award a bid for construction sometime in December.  The board will decide whether to go with a 4 or 6 classroom addition based on cost once the bidding process begins.   The plan is to have the new classrooms open for school by the beginning of the next school year.

See the three possible schematic designs below.

In other BISD business:

*BISD introduced Officer Fred Bastardo as the new BHS security officer.  Bastardo said that he is looking to start a campus crime stoppers program.

*Trustees approved the discontinuation of the D.A.T.E grant incentive for personnel.

*Trustees approved the adoption of “Make Education a Priority” Resolution.  So far, 101 school districts have adopted this resolution to unify and show strength as the new legislative session gets close.

*Trustees approved the 2010-2011 School Health Advisory Committee.

*Trustees approved TASB localized Policy Update 88 as well as District/Campus Improvement Plans

*Trustees approved the District’s and campuses improvement plans.

option1

Option one is for 4 additional classrooms which would add 6636 sq ft and an 88 additional student capacity.

option2

Option two is for 6 additional classrooms which would add 8941 sq ft and a 132 additional student capacity.

Option3

Option three is also for 6 additional classrooms in an alternate configuration that would also add 8941 sq ft and a 132 additional student capacity.